[ARCHIVED] Highway 67 / Kelley's Rd Construction Updates

Traffic cone on a road and text

Colorado Department of Transportation (CDOT) has begun construction activities at the intersection of Highway 67 and Kelley's road. Traffic flow may be affected intermittently until early summer 2021 - please plan accordingly.


Latest Updates


4/5/21 - Road Closure. Kelly's Rd. will be closed between HWY 67 and Sundance St. through 4/16/21 for safety reasons during work hours. This closure is subject to change. Please check back for updates. Questions or concerns should be directed to CDOT at 719-581-2301. Please see photo below for detour route.

Woodland Park Detour Map

3/29/21 - During the week of March 29 through April 2 , crews will be working north and south bound on CO 67 at Kelley's Road Intersection. Right lane will be closed in both directions. Flaggers will be present on side streets to help with visibility issues. Please remember to obey posted speed limits and watch for workers. Questions or concerns should be directed to CDOT at 719-581-2301. 

03/15/21 - During the week of March 15 though March 19, the CDOT contractor will be waiting for the snow to clear. Once snow is clear, they will begin pulling wire. Questions or concerns should be directed to CDOT at 719-581-2301. 

03/08/21 - During the week of March 8 through 12, the CDOT contractor will begin setting pull-boxes at the intersection of Kelley's Road and US Highway 67.  Additionally, work will begin along the Highway 67 corridor to include demolition and reconstruction of ADA pedestrian ramps.  Questions or concerns should be directed to CDOT at 719-581-2301.

03/02/21 - During the week of March 1 through 5, the CDOT contractor will continue performing subterranean directional drilling at the intersection of Kelley's Road and US Highway 67. Work next week will include setting pull-boxes and beginning to demolish and replace ADA pedestrian ramps along the Highway 67 corridor.  Questions or concerns should be directed to CDOT at 719-581-2301. 

02/19/21 - During the weeks of February 15 through 26, the CDOT contractor will not be working at the intersection of Kelley's Road and US Highway 67.  Questions or concerns should be directed to CDOT at 719-581-2301.

02/08/21 - During the week of February 8 through 12, the CDOT contractor will work on building the electrical service for the future traffic signal at the intersection of Kelley's Road and US Highway 67. Questions or concerns should be directed to CDOT at 719-581-2301.

02/01/21 - During the week of February 1 through 5, the CDOT contractor will continue to work on potholing and performing subterranean directional drilling at the intersection of Kelley's Road and US Highway 67.  Questions or concerns should be directed to CDOT at 719-581-2301. 